Building services procurement plan
The procurement plan is updated monthly, dates are estimates and are subject to change without notice.
Key:
- estimated date (Est)
- actual date (Act).
Note: Remote contracts will be subject to access to the remote community.
| Region | Electorate | Program | Project description | Tier | Advertising target | Advertising period (weeks) | Tender committal |
|---|---|---|---|---|---|---|---|
| ALICE SPRINGS | NAMATJIRA | Capital Works | ALICE SPRINGS CORRRECTIONAL CENTRE - HIGH AND LOW VOLTAGE INFRASTRUCTURE UPGRADES | Tier 5 ($5million and Greater) | Act Nov 25 | 3 | Act Apr 26 |
| ALICE SPRINGS | BRAITLING | Minor Works | ALICE SPRINGS - 16 POWER STREET - CONSTRUCT NEW CORE SHED EXTENSION | Tier 3 ($200 000 to $500 000) | Act Jun 26 | 3 | Est Sep 26 |
| ALICE SPRINGS | BRAITLING | Capital Works | ALICE SPRINGS - DESIGN AND CONSTRUCT OF THE GILLEN OVAL MULTI SPORTS PRECINCT | Tier 5 ($5million and Greater) | Act Mar 26 | 6 | Est Jul 26 |
| ALICE SPRINGS | BRAITLING | Capital Works | ALICE SPRINGS - DESIGN DOCUMENT AND CONSTRUCT ALICE SPRINGS MULTICULTURAL CENTRE (ASMC) | Tier 5 ($5million and Greater) | Act Mar 26 | 6 | Est Jul 26 |
| ALICE SPRINGS | NAMATJIRA | Minor Works | ALICE SPRINGS CORRECTIONAL CENTRE -REINTEGRATION FACILITY - UPGRADE FIRE SYSTEM | Tier 4 ($500 000 - $5 million) | Act Apr 26 | 6 | Est Jul 26 |
| ALICE SPRINGS | NAMATJIRA | Minor Works | ALICE SPRINGS CORRECTIONAL CENTRE - REFURBISH H BLOCK ADMINISTRATION | Tier 3 ($200 000 to $500 000) | Est Jul 26 | 4 | Est Oct 26 |
| ALICE SPRINGS | NAMATJIRA | Minor Works | ALICE SPRINGS REGION - ARID ZONE RESEARCH INSTITUTE HOUSES - PERIMETER FENCING UPGRADES | Tier 3 ($200 000 to $500 000) | Act Feb 26 | 2 | Act Jun 26 |
| ALICE SPRINGS | ARALUEN | Minor Works | ARALUEN BASE BUILDING RECTIFICATION WORKS | Tier 3 ($200 000 to $500 000) | Est Aug 26 | 4 | Est Nov 26 |
| ALICE SPRINGS | GWOJA | Minor Works | ALICE SPRINGS REGION - KINTORE (WALUNGURRU) SCHOOL - DESIGN, DOCUMENTATION, CERTIFICATION AND CONSTRUCTION OF NEW MODULAR ABLUTION BLOCK, INCLUDING DEMOLITION OF EXISTING | Tier 4 ($500 000 - $5 million) | Act Mar 26 | 6 | Est Jul 26 |
| ALICE SPRINGS | NAMATJIRA | Minor Works | ALICE SPRINGS REGION - WATARRKA NATIONAL PARK - SUPPLY, DELIVERY AND INSTALLATION OF WILTJA STRUCTURE AND ASSOCIATED INTERPRETIVE ELEMENTS | Tier 4 ($500 000 - $5 million) | Act Feb 26 | 4 | Act Jun 26 |
| ALICE SPRINGS | ARALUEN | Specific Maintenance | ALICE SPRINGS HOSPITAL - REPLACEMENT OF MAIN ELECTRICAL SWITCHBOARD | Tier 4 ($500 000 - $5 million) | Act May 26 | 4 | Est Aug 26 |
| ALICE SPRINGS | ARALUEN | Minor Works | ALICE SPRINGS HOSPITAL - SUSPENDED CEILING REMEDIATION - PRIORITY AREAS | Tier 3 ($200 000 to $500 000) | Est Jul 26 | 4 | Est Oct 26 |
| DARWIN | GOYDER | Minor Works | ACACIA HILLS - BUSH FIRES NT HEADQUARTERS - ADDITIONAL SECURITY AND SAFETY UPGRADES | Tier 3 ($200 000 to $500 000) | Act Jun 26 | 2 | Est Sep 26 |
| DARWIN | CASUARINA | Minor Works | DRIPSTONE SECONDARY COLLEGE - DESIGN, DOCUMENT AND CONSTRUCT UPGRADE OF EXISTING SCIENCE LABORATORY | Tier 3 ($200 000 to $500 000) | Act Apr 26 | 3 | Est Jul 26 |
| DARWIN | SANDERSON | Minor Works | ARAFURA STADIUM - GYM ACCESS UPGRADES | Tier 3 ($200 000 to $500 000) | Act Nov 25 | 3 | Act Feb 26 |
| DARWIN | NELSON | Minor Works | DEFENCE ACCOMODATION PRECINCT - CONSTRUCT NEW MULTIPLE VEHICLE CARPORTS AND BUS SHELTERS | Tier 3 ($200 000 to $500 000) | Act Oct 25 | 3 | Act Mar 26 |
| DARWIN | NELSON | Minor Works | DEFENCE ACCOMODATION PRECINCT - LAUNDRY VERANDAH EXTENSIONS | Tier 4 ($500 000 - $5 million) | Act Oct 25 | 6 | Act Feb 26 |
| DARWIN | BLAIN | Minor Works | MOULDEN PRIMARY SCHOOL - ACCESS RAMP AND STAIR UPGRADES | Tier 3 ($200 000 to $500 000) | Act Jan 26 | 3 | Act Mar 26 |
| DARWIN | DARWIN | Period Contract | REPAIRS AND MAINTENANCE OF GROUP 7 - AIRCONDITIONING PLANT AND EQUIPMENT FOR A PERIOD OF 36 MONTHS | Tier 5 ($5million and Greater) | Act Oct 25 | 6 | Act May 26 |
| DARWIN | DARWIN | Period Contract | DARWIN REGION - REPAIRS AND MAINTENANCE OF PLUMBING SEWERAGE SYSTEMS AND EQUIPMENT TO VARIOUS NT GOVERNMENT ASSETS FOR A PERIOD OF 36 MONTHS | Tier 4 ($500 000 - $5 million) | Act Apr 26 | 3 | Est Jul 26 |
| DARWIN | FONG LIM | Specific Maintenance | HIDDEN VALLEY MOTOR SPORTS COMPLEX - EXTERNAL PAINTING AND WINDOW REPAIRS | Tier 3 ($200 000 to $500 000) | Act Feb 26 | 2 | Act Apr 26 |
| DARWIN | FANNIE BAY | Minor Works | MUSEUM AND ART GALLERY OF THE NT - REPLACE 8 SWITCHBOARDS | Tier 3 ($200 000 to $500 000) | Est Jul 26 | 2 | Est Sep 26 |
| DARWIN | NELSON | Minor Works | PALMERSTON REGIONAL HOSPITAL - CHEMICAL DOSING UPGRADE AND BMS INTEGRATION | Tier 3 ($200 000 to $500 000) | Est Jul 26 | 4 | Est Oct 26 |
| DARWIN | FANNIE BAY | Minor Works | PARAP PRIMARY SCHOOL - CHILLED WATER PLANT UPGRADE | Tier 4 ($500 000 - $5 million) | Act Feb 26 | 4 | Act May 26 |
| DARWIN | DARWIN | Minor Works | PETER MCAULAY CENTRE - ELECTRICAL INFRASTRUCTURE UPGRADE STAGE 2 | Tier 4 ($500 000 - $5 million) | Act Nov 25 | 9 | Act Mar 26 |
| DARWIN | CASUARINA | Minor Works | ROYAL DARWIN HOSPITAL - SEWER ACCESS CHAMBER MANHOLE UPGRADE | Tier 3 ($200 000 to $500 000) | Act Jun 26 | 3 | Est Sep 26 |
| DARWIN | CASUARINA | Minor Works | ROYAL DARWIN HOSPITAL - REPLACEMENT OF LAUNDRY TANKS AND ASSOCIATED PIPEWORK | Tier 3 ($200 000 to $500 000) | Act Jun 26 | 3 | Est Sep 26 |
| DARWIN | NELSON | Minor Works | DARWIN - PETER MCAULAY CENTRE - FIT-OUT OF EXISTING ROOM TO ENABLE RELOCATION OF RADIO COMMUNICATIONS EQUIPMENT | Tier 3 ($200 000 to $500 000) | Act Jan 26 | 4 | Act Apr 26 |
| DARWIN | CASUARINA | Capital Works | DARWIN - LEANYER RECREATIONAL PARK - DESIGN AND CONSTRUCT NORTHERN SUBURBS YOUTH HUB | Tier 4 ($500 000 - $5 million) | Act Mar 26 | 6 | Est Jul 26 |
| DARWIN | DARWIN VARIOUS | Capital Works | DARWIN REGION - CHARLES POINT REEF FISH PROTECTION AREA - DESIGN, CONSTRUCT AND DEPLOY ARTIFICIAL REEF MODULES | Tier 4 ($500 000 - $5 million) | Act Mar 26 | 2 | Est Jul 26 |
| DARWIN | SPILLET | Minor Works | BERRIMAH FARM - NEW BIOSECURITY AND ANIMAL WELFARE SHED | Tier 3 ($200 000 to $500 000) | Est Jul 26 | 4 | Est Oct 26 |
| DARWIN | TIWI | Minor Works | ROYAL DARWIN HOSPITAL - UPGRADE EXISTING AND INSTALL NEW FIRE DOORS | Tier 3 ($200 000 to $500 000) | Est Jul 26 | 3 | Est Oct 26 |
| DARWIN | MILLNER | Minor Woks | HARNEY HOUSE INTERNAL AND EXTERNAL REFURBISHMENT UPGRADES AND ASSOCIATED WORKS | Tier 3 ($200 000 to $500 000) | Act May 26 | 4 | Est Oct 26 |
| DARWIN | GOYDER | Capital Works | BEES CREEK NATIONAL CRITICAL CARE AND TRAUMA RESPONSE CENTRE WAREHOUSE AND ROAD UPGRADE | Tier 4 ($500 000 - $5 million) | Est Oct 26 | 4 | Est Dec 26 |
| DARWIN | ARAFURA | Capital Works | MANINGRIDA POLICE STATION - STAGE 2 - HOUSING | Tier 4 ($500 000 - $5 million) | Est Jul 26 | 4 | Est Sep 26 |
| DARWIN | DALY | Capital Works | DALY RIVER POLICE STATION - UPGRADE | Tier 5 ($5million and Greater) | Est Nov 27 | 4 | Est Dec 27 |
| DARWIN | DARWIN | Period Contract | DARWIN REGION - REPAIRS AND MAINTENANCE OF PRIME AND STANDBY GENERATORS, BORE PUMP ENGINES AND OTHER ASSOCIATED EQUIPMENT TO NT GOVERNMENT ASSETS FOR A PERIOD OF 36 MONTHS | Tier 4 ($500 000 - $5 million) | Act Jan 26 | 4 | Act May 26 |
| DARWIN | SPILLETT | Specific Maintenance | BERRIMAH FIRE STATION AND EMERGENCY SERVICES BUILDING - FULL EXTERNAL PAINTWORK INCLUDING INTERNAL WALLS OF ENGINE BAY CEILING | Tier 3 ($200 000 to $500 000) | Act Mar 26 | 3 | Act Jun 26 |
| GOVE | MULKA | Capital Works | NHULUNBUY CYCLONE SHELTER | Tier 5 ($5million and Greater) | Est Jul 26 | 5 | Est Oct 26 |
| KATHERINE | KATHERINE | Capital Works | KATHERINE - KINTORE STREET SCHOOL (O'SHEA CAMPUS) - CONSTRUCTION OF NEW DROP OFF AND PICK UP AREA | Tier 3 ($200 000 to $500 000) | Act Dec 25 | 6 | Act Feb 26 |
| KATHERINE | ARNHEM | Specific Maintenance | KATHERINE REGION - NGUKURR - DEMOLITION OF OLD HEALTH CLINIC | Tier 4 ($500 000 - $5 million) | Act Feb 26 | 4 | Act Jun 26 |
| KATHERINE | KATHERINE | Minor Works | KATHERINE HIGH SCHOOL - REPLACEMENT OF VARIOUS AIR HANDLING UNITS | Tier 3 ($200 000 to $500 000) | Act Nov 25 | 4 | Act Jun 26 |
| KATHERINE | BARKLY | Capital Works | KATHERINE REGION - BORROLOOLA - CONSTRUCT NEW HEALTH CENTRE, RENAL UNIT AND MORTUARY | Tier 5 ($5million and Greater) | Act Dec 25 | 11 | Est Jul 26 |
| KATHERINE | KATHERINE | Minor Works | KATHERINE POLICE STATION -NEW AIR-CONDITIONING SYSTEM TO GYM | Tier 3 ($200 000 to $500 000) | Act Dec 25 | 6 | Act Apr 26 |
| KATHERINE | KATHERINE | Minor Works | KATHERINE - SCHOOL OF THE AIR - DESIGN AND CONSTRUCT NEW TOILET FACILITIES AND MODIFY EXISTING | Tier 3 ($200 000 to $500 000) | Act Sep 25 | 5 | Act Mar 26 |
| KATHERINE | KATHERINE | Capital Works | KATHERINE RURAL CAMPUS - CONSTRUCTION OF NEW SKILLS AND TRAINING CAMP AND UPGRADE OF EXISTING FACILITIES | Tier 5 ($5million and Greater) | Act Mar 26 | 4 | Act Jun 26 |
| TENNANT CREEK | BARKLY | Minor Works | TENNANT CREEK - GOVERNMENT COMPLEX - DEPARTMENT OF LOGISTICS AND INFRASTRUCTURE BUILDING - OFFICE FIT OUT | Tier 4 ($500 000 - $5 million) | Act Dec 25 | 5 | Act Feb 26 |
| TENNANT CREEK | TENNANT CREEK | Period Contract | TENNANT CREEK REGION - PANEL CONTRACT FOR REPAIRS, MAINTENANCE, AND INSTALLATION OF PLUMBING AND HYDRAULIC SYSTEMS FOR A PERIOD OF 36 MONTHS | Tier 4 ($500 000 - $5 million) | Act Jul 25 | 3 | Act Feb 26 |
Get the printable version: Building services procurement plan PDF (202.5 KB).