Nightcliff Jetty upgrades

The Department of Logistics and Infrastructure is undertaking upgrade works to Nightcliff Jetty.

MMC Australia Pty Ltd has been awarded the contract to complete the program of works.

Scheduled start date: Monday 11 May 2026.

Expected completion date: late July 2026.

Works will occur Monday to Friday from 7am to 5pm and Saturday 8am to 3pm.

Works include

  • Surface corrosion treatment of jetty columns.
  • High pressure water blasting of the walkway structure and jetty head in preparation for repainting.
  • Removal of timber decking for high pressure water blasting, installation of new timber decking where required and reinstallation of decking to close gaps between each board to 10mm.
  • Repairs and installation of handrails at jetty head.
  • Installation of gate at top of the steps at jetty head.
  • Installation of additional structural support where required.

Public safety

To maintain public safety, access to the jetty will be adjusted at different stages of the works period:

  • Jetty walkway access: open 11 to 17 May and 29 June to 10 July.
  • Jetty head access: open 29 June to 10 July.
  • Full closure: outside these dates, the entire jetty will be closed until works are complete.

During Term 2 school holidays, the jetty will be open for the final 2 weeks (29 June to 10 July). Where it is safe to do so, work will continue underneath the structure, allowing the community to keep enjoying the jetty as upgrades progress.

MMC Australia Pty Ltd will mobilise and demobilise daily to minimise impacts on nearby vendors such as food trucks.

The carpark will remain open. Pedestrians and motorists are asked to take caution during this time and comply with all traffic management and signage in place.