Projects in preparation or tender process

Region Program Project description Tier Advertising target Advertising period (weeks) Tender committal
Alice Springs Capital Works Alice Springs - Finke Road - Supply Delivery and Installation of Two New Culverts at Distances of 129 and 132km Tier 4 $500,000 - $5M Act Mar - 26 4 Est Aug - 26
Alice Springs Capital Works Hamilton Down Youth Camp Access - Gravel Resheet 0 - 6km & Construct 3 Concrete Floodways Tier 4 $500,000 - $5M Est Nov - 26 4 Est Jan - 27
Alice Springs Capital Works Hamilton Downs Youth Camp Access - Gravel Resheet 12 - 17km Tier 4 $500,000 - $5M Est Oct - 26 4 Est Jan - 27
Alice Springs Minor New Works Larapinta Drive - Replace Streetlighting between Lovegrove Drive to Mparntwe Drive Tier 4 $500,000 - $5M Act Dec - 25 6 Act Mar - 26
Alice Springs Capital Works Larapinta Drive - Replace Armco Pipe at 236km Tier 3 $200,000 - $500,000 Est Aug - 26 4 Est Nov - 26
Alice Springs Capital Works Mulga Park Road - Gravel Resheet 85 - 108km Tier 4 $500,000 - $5M Est Sep - 26 4 Est Jan - 27
Alice Springs Capital Works Napperby Road - Gravel Resheet 21 - 27km and Construct Concrete margin on Floodway at 59km Tier 4 $500,000 - $5M Est Oct - 26 4 Est Dec - 26
Alice Springs Capital Works Sandover Highway - Upgrade To Seal Standard 170 - 197km (major Project) Tier 5 $5M and Greater Est Sep - 26 8 Est Dec - 26
Alice Springs Capital Works Sandover Highway - Upgrade To Seal Standard 197 - 217km (major Project) Tier 5 $5M and Greater Est Apr - 27 4 Est Aug - 27
Alice Springs Capital Works Santa Teresa Road - Upgrade to Seal 40 - 63km Tier 5 $5M and Greater Est Aug - 26 4 Est Nov - 26
Alice Springs Capital Works Outback Way - Plenty Highway - Upgrade to Seal 170 - 209km Tier 5 $5M and Greater Est Jan - 27 4 Est Apr - 27
Alice Springs Capital Works Mereenie Loop - Larapinta Drive Upgrade to Seal 168 - 193.5km Tier 5 $5M and Greater Est Aug - 26 4 Est Dec - 26
Alice Springs Minor New Works South Terrace - Upgrade Shared Path Between Tom Brown Roundabout and Stephens Road Tier 3 $200,000 - $500,000 Act Feb - 26 4 Act Jul - 26
Alice Springs Minor New Works Stuart Highway - LED Upgrades Schwarz Cresent To Stott Terrace Tier 4 $500,000 - $5M Act Mar - 26 4 Act Jun - 26
Alice Springs Capital Works Stuart Highway/Schwarz Crescent Intersection - Install Traffic Lights And Schwarz Crescent Construct Roundabout Tier 5 $5M and Greater Est Aug - 26 4 Est Nov - 26
Alice Springs Capital Works Willowra Rd - Lift & Gravel Re-sheet 49 - 56km Tier 4 $500,000 - $5M Est Sep - 26 4 Est Dec - 26
Alice Springs Cyclic Maintenance Alice Springs Region - Various Zones - Maintenance Grading and Minor Repairs of Unsealed Roads, Shoulders and Airstrips for a Period of 36 Months Tier 5 $5M and Greater Act Feb - 26 6 Est Aug - 26
Alice Springs Cyclic Maintenance Alice Springs Region - Sealed Pavement Maintenance for a Period of 36 Months Tier 5 $5M and Greater Act Apr - 26 5 Est Aug - 26
Alice Springs Cyclic Maintenance Alice Springs - Western Region - Repairs & Maintenance of Gravel Roads and Airstrips for a Period of 36 months Tier 5 $5M and Greater Act Jul - 26 3 Est Nov - 26
Alice Springs Cyclic Maintenance Alice Springs - Eastern Region - Repairs & Maintenance of Gravel Roads and Airstrips for a Period of 36 months Tier 5 $5M and Greater Act Jul - 26 3 Est Nov - 26
Darwin Capital Works Ringwood Road - Gravel Resheet at Various Locations Tier 3 $200,000 - $500,000 Act Jun - 26 2 Est Aug - 26
Darwin Capital Works Pirlangimpi Road (Tiwi Islands) - Upgrade and Seal 0 -15km Tier 5 $5M and Greater Est Aug - 26 4 Est Jan - 27
Darwin Cyclic Maintenance Darwin Region - Maintenance of Bus Stops for a Period of 60 Months Tier 4 $500,000 - $5M Act Mar - 26 4 Act Jun - 26
Darwin Minor New Works Bagot Road/Stuart Highway Intersection - Construct New Road Safety Barrier Tier 3 $200,000 - $500,000 Act Jul - 26 5 Est Nov - 26
Darwin Minor New Works Bathurst Island - Aerodrome - Fencing Relocation Tier 3 $200,000 - $500,000 Est Oct - 26 4 Est Jan - 27
Darwin Capital Works Chung Wah Terrace - Widen Carriageway Between Temple Terrace and Forrest Parade and Extend Left Turn Lane into Forrest Parade Tier 3 $200,000 - $500,000 Est Sep - 26 6 Est Dec - 26
Darwin Minor New Works Darwin Traffic Signal Control Upgrade – Replacement to TSC-4 Standards Across the Road Network Tier 3 $200,000 - $500,000 Est Oct - 26 5 Est Dec - 26
Darwin Capital Works Fountain Head Road - Pavement Rehabilitation 0 - 1.6km Tier 4 $500,000 - $5M Est Aug - 26 6 Est Nov - 26
Darwin Capital Works Kakadu Highway - Culvert Extension Various Locations Between 92 - 106.6km Tier 4 $500,000 - $5M Est Aug - 26 7 Est Nov - 26
Darwin Specific Maintenance National Network - Stormwater Drainage CCTV Inspection Tier 4 $500,000 - $5M Est Sep - 26 6 Est Dec - 26
Darwin Capital Works Port Keats Road - Palumpa To Wadeye - Upgrade And Seal (major Project) Tier 5 $5M and Greater Est Oct - 26 8 Est Feb - 27
Darwin Capital Works Stuart Highway - Pavement Strengthening and Widening between 113 - 115Km Tier 4 $500,000 - $5M Est Oct - 26 4 Est Feb - 27
Darwin Capital Works Stuart Highway/Bees Creek Road - Intersection Upgrade Tier 4 $500,000 - $5M Act Apr - 26 6 Act Jul - 26
Darwin Minor New Works Warruwi Barge Landing - Drainage and Signage Upgrades Tier 3 $200,000 - $500,000 Act Feb - 26 4 Act May - 26
Gove Specific Maintenance East Arnhem Region - Central Arnhem Road - Gravel Resheet 426 - 434km Tier 4 $500,000 - $5M Act Feb - 26 5 Act May - 26
Darwin Capital Works Darwin Region - Kakadu – Upgrade - Gimbat Road 20.5km to 25.5km and Gunlom Road 2km to 8.6km Tier 5 $5M and Greater Act Mar - 26 9 Est Aug - 26
Gove Capital Works Central Arnhem Road - Upgrade and Seal - 544 - 645km Tier 5 $5M and Greater Est Sep - 26 9 Est Mar - 27
Katherine Capital Works Beasley Road - Upgrade to Seal 3 - 4km Tier 4 $500,000 - $5M Act Mar - 26 4 Act Jun - 26
Katherine Capital Works Buntine Highway - Upgrade 5 Heavy Vehicle Rest Areas - 16.6km, 44km, 60.7km, 204.2km, & 257.4km Tier 4 $500,000 - $5M Est Oct - 26 8 Est Feb - 27
Katherine Capital Works Buntine Highway - Upgrade to Two Lane Seal Standard 256 - 278km (major Project) Tier 5 $5M and Greater Est Oct - 26 6 Est Feb - 27
Katherine Capital Works Central Arnhem Road - Upgrade and Seal - 56 - 60km Tier 5 $5M and Greater Est Apr - 27 9 Est Oct - 27
Katherine Capital Works Buntine Highway - Upgrade to Two Lane Seal Standards 10 - 26km (major Project) Tier 5 $5M and Greater Est Nov - 26 8 Est Mar - 27
Katherine Capital Works Katherine Region - Central Arnhem Road - Upgrade to Two Lane Seal from 15 - 29.4km (Major Project) Tier 5 $5M and Greater Act Jan - 26 8 Est Aug - 26
Katherine Capital Works Design and Construct - Victoria Highway - Shoulder Rehabilitation and Culvert Upgrades 390 - 411Km Tier 5 $5M and Greater Est Aug - 26 6 Est Nov - 26
Katherine Minor New Works Katherine Region - Numbulwar Road - Floodway Installations and Barge Landing Repairs - Culvert Invert Strengthening & Capacity Upgrade Tier 3 $200,000 - $500,000 Act Apr - 26 4 Est Aug - 26
Katherine Minor New Works Port Roper Road - Floodway Replacements Tier 3 $200,000 - $500,000 Est Aug - 26 3 Est Nov - 26
Katherine Capital Works Stuart Highway - Strengthening and Widening 251 - 255km Tier 4 $500,000 - $5M Act Jan - 26 6 Est Aug - 26
Katherine Capital Works Stuart Highway - Strengthening and Widening 428 - 431km Tier 4 $500,000 - $5M Est Aug - 26 4 Est Nov - 26
Katherine Capital Works Stuart Highway/Tamboran - Intersection upgrade - Kyalla 117km Access Tier 4 $500,000 - $5M Est Oct - 26 4 Est Dec - 26
Katherine Capital Works Victoria Highway - Pavement Rehabilitation 257 - 257.5 and 273 - 275km Tier 4 $500,000 - $5M Est Aug - 26 6 Est Dec - 26
Katherine Specific Maintenance Victoria Highway - Pavement Repairs Between 286 - 469km - Various Section Tier 3 $200,000 - $500,000 Est Feb - 27 4 Est Apr - 27
Katherine Capital Works Victoria Highway - Pavement Strengthening and Widening 118 - 124km Tier 5 $5M and Greater Est Nov - 26 4 Est May - 27
Tennant Creek Capital Works Ali Curung Aerodrome - Seal and Line Mark Airstrip Tier 4 $500,000 - $5M Est Aug - 26 6 Est Nov - 26
Tennant Creek Capital Works Barkly Highway - New Truck Parking Bay between Rockhampton Bar and Barkly Homestead Tier 4 $500,000 - $5M Est Feb - 27 6 Est Jun-27
Tennant Creek Capital Works Barkly Highway - Pavement Strengthening and Widening 430 - 434km Tier 4 $500,000 - $5M Est Feb - 27 6 Est Jun-27
Tennant Creek Capital Works Barkly Highway - Strengthening and Widening 386 - 399 & 408 - 410km Tier 5 $5M and Greater Est Feb - 27 6 Est Jun-27
Tennant Creek Capital Works Barkly Highway - Strengthening and Widening - 378 - 386km Tier 4 $500,000 - $5M Est Feb - 27 6 Est Jun-27
Tennant Creek Capital Works Barkly Highway - Strengthening and Widening - 345 - 349km Tier 4 $500,000 - $5M Est Feb - 27 6 Est Jun-27
Tennant Creek Capital Works Barkly Highway - Strengthening and Widening 321 - 328km Tier 4 $500,000 - $5M Est Feb - 27 6 Est Jun-27
Tennant Creek Capital Works Elkedra Property Access - Gravel Resheet 0.7km & Construct Floodway's Tier 4 $500,000 - $5M Est Aug - 26 4 Est Nov - 26
Tennant Creek Capital Works Tennant Creek Region - Murray Downs Road - Gravel Resheet 18 - 35km Tier 4 $500,000 - $5M Act Dec - 25 6 Act Apr - 26
Tennant Creek Minor New Works Paterson Street - New Banner Holders Tier 3 $200,000 - $500,000 Est Aug - 26 3 Est Sep - 26
Katherine Capital Works Western Creek Road Upgrade (major prject)
Package A - 0.00km to 15.00km
Package B - 15.00km to 30.00km
Package C - 30.00km to 46.50km
Tier 5 $5M and Greater Est Sep - 27 6 Est Dec - 27
Darwin Capital Works Maningrida Aerodrome - Fencing Upgrade Tier 4 $500,000 - $5M Est Aug - 26 4 Est Nov - 26
Darwin Capital Works Arnhem Highway Duplication - Stuart Highway to Kostka Road Tier 5 $5M and Greater Est Nov - 26 6 Est Mar - 27