Housing infrastructure procurement plan
The procurement plan is updated monthly, dates are estimates and are subject to change without notice.
Key:
- estimated date (Est)
- actual date (Act).
Note: Remote contracts will be subject to access to the remote community.
The table below is accurate as of 31 March 2025.
Region | Electorate | Program | Project description | Tier | Advertising target | Advertising period (weeks) | Tender committal |
---|---|---|---|---|---|---|---|
All Regions | All Regions | Remote Land Servicing | All of NT - Panel Contract for Engineering Services to Support Land Servicing for a Period of 36 Months | Tier 5 ($5M and greater) | ACT JAN 25 | 5 | EST JUL 25 |
Big Rivers | Katherine | New Builds RCH | Katherine Region - Minyerri - Lot 141 - Construction of 6 Dwellings | Tier 5 ($5M and greater) | ACT NOV 24 | 9 | EST MAY 25 |
Darwin | Nightcliff | Land Development | Kulaluk Drainage and Pavement Upgrades | Tier 5 ($5M and greater) | ACT NOV 24 | 5 | EST MAY 25 |
Darwin | Nelson | Land Development | Holtze - Part B Land Release Infrastructure | Tier 5 ($5M and greater) | EST JUN 25 | 6 | EST DEC 25 |
Tennant Creek | Barkly | GEH | Barkly Region - Rockhampton Downs (Wogyala) and Newcastle Waters - Security Upgrades and Refurbishment Works to Existing Government Employee Housing (GEH) Homes | Tier 3 ($100,000 - $499,999) | ACT APR 25 | 4 | EST JUN 25 |
Tennant Creek | Barkly | GEH | Barkly Region - Imangara and Wutungurra (Epenarra) - Security Upgrades and Refurbishment Works to Existing Government Employee Housing (GEH) Homes. | Tier 3 ($100,000 - $499,999) | ACT APR 25 | 4 | EST JUN 25 |
West Arnhem | Arnhem | Remote Land Servicing | Darwin Region - Maningrida - Subdivision Stage 3 - Construction of Civil Works and Services | Tier 5 ($5M and greater) | ACT DEC 24 | 10 | EST JUN 25 |
Get the printable version: Housing infrastructure procurement plan PDF (292.7 KB).